Speaking on Wednesday, Minister of Power, Works and Housing, Babatunde Fashola has revealed why the ministry couldn't carry out a project in 2017.
Minister of Power, Works and Housing, Babatunde Fashola
The Minister of Power, Works and Housing, Babatunde Fashola (SAN), has given reasons why the works ministry was unable to execute capital projects in 2017.
Speaking on Wednesday when he appeared before the Senate Committee on Works to defend 2018 budget proposed by his ministry, Fashola blamed it on the late passage of the 2017 budget.
A member of the committee, Senator Barnabas Gemade had asked why the ministry (Works) had zero performance of capital projects in 2017.
Fashola said, “The 2017 budget was passed in June. The procurement law requires a procurement plan which took till September. In following this law, the first release was in August. Most of the projects were going through procurement formalities such as tax identity, contract terms, even construction companies went on holidays. So, there were so many things.”
Chairman of the committee, Senator Kabiru Gaya, then asked about the amount of projects that were not procured in 2017 since there was a rollover of projects from 2016.
Fashola was unable to respond to the question, stating that even the Director of Planning in the ministry could not give a definite answer. He, however, pleaded with the committee to bring a detailed report later.
The minister said, “It is a tough task. We may be allowed to submit those details. The ending solution, which has not been found favourable, is that once you appropriate for a project in a particular budget, it should not be lined up in another year.”
Fashola said the country could not finance new projects every year due to its enormous nature.
He added, “Most of these roads are between 50km and 100km. In your states, 5km (road) takes 24 months. Then if we have more in a budget, we cannot finish them. It is not what we want. Our resources are not increasing in an exponential manner, compared to our projects.”
The committee then resolved that the projects in 2017, which were not procured, should be rolled over into the 2018 budget and re-presented in the report in a week.