Posted by Samuel on Fri 01st Mar, 2024 - tori.ng

Although the developer was alleged to have used a C-of-O for GRA to obtain the building permit, ECTDA did not demolish the two permitted buildings (a one-storey building and a security house) in order to allow the developer to regularise the structures with proper application with the correct plot and zone.

Breathe Restaurant & Lounge

The Enugu State government has declared the demolition of what they term as 'unauthorized structures' at Breathe Restaurant & Lounge situated in Independence Layout, Enugu.

The State Capital Territory Development Authority (ECTDA), which carried out the demolition on Thursday, cited lack of title documents, fraudulent submission of Certificate of Occupancy (C-of-O), construction of more buildings than were approved, change of purpose of building permit without approval, among others as the reason for the exercise.

Although the developer was alleged to have used a C-of-O for GRA to obtain the building permit, ECTDA did not demolish the two permitted buildings (a one-storey building and a security house) in order to allow the developer to regularise the structures with proper application with the correct plot and zone.

In statement a issued on Friday, the agency said it acted following the revocation of the withdrawal of building plan/permit in line with the powers conferred on it by the law, and based on item 11 of the affidavit sworn by the developer, Ndubuisi Madueke, in support of his application for building permit.

In the said item 11, the developer had sworn: “If at any point it is found that any information stated in my drawing is false, or that I deviate from the contents of the building drawing submitted to the authority containing my intended development plan, that this owner/builder permit is deemed invalid and automatically stand revoked.”

SaharaReporters reports that before the demolition, the ECTDA raised the alarm in a media briefing last week over what it described as "proliferation of fake title documents, forged building approvals, manipulation of permits, and illegal structures in parts of the Enugu metropolis," saying it had revoked several of the permits/approvals for such structures, as they posed a danger to human and environmental safety.

A February 16, 2024 letter addressed to the proprietor of the restaurant with reference number ENS/ECTDA/ADM/376/VOL.1/27, is entitled “Withdrawal of Approved Building Plan/Permit”.

In the letter, the Executive Chairman of ECTDA wrote: “I hereby write to refer to the above subject matter for strict compliance of the Enugu Municipal Master Plan, and inform you that your approval for building construction issued by the agency with plan No. ECTDA/EPC/1380 DATED 2ND May 2023 has been withdrawn for the following reasons:

“i. Non-payment of necessary fees to the Government for Building Plan Approval/Permit.

“ii. Fraudulent submission of Certificate of Occupancy (C of O) of a property at Ekulu River Layout in GRA to obtain approval/permit for building of a property at Independence Layout.

“iv. Construction of five (5) building structures as against two (2) structures in the building plan.

“v. Change of purpose clause without approval.

“vi. Failure to abide/comply with all application laws, requirements, ordinances, building codes and zoning regulations, as contained in the Owner/Builder Permit Affidavit form signed and sworn in a competent court of law by your own very self (see item 7 of the copy attached).

“vii. Failure to notify the agency of any addition, deletions, or changes to any information that you provided on the affidavit disclosure (see item 10).”

The ECTDA chairman also cited item 11 of the affidavit when the developer declared his Owner/Builder Plan Permit was “deemed invalid and automatically stand revoked” should he be found to have given false information or deviated from the building plans submitted in pursuit of the application.

SaharaReporters earlier reported that the state government had demolished many houses, hotels and a multi-million farm, most of them without notice and others with less than 24 hours' notice.